SAMRUK ENERGY

EFFICIENT HIGH-TECH
OPERATING ENERGY COMPANY

News

10.05.24

Samruk-Green Energy successfully sells over 12,000 green certificates

09.05.24

Victory Day congratulations from Kairat Maxutov, Chairman of the Board of “Samruk-Energy” JSC

06.05.24

Announcing the winners of the children's drawing contest

About company

"Samruk-Energy" JSC is the largest diversified electric power holding company with a primary objective of establishing a highly efficient energy supply system to support the sustainable development of all sectors in Kazakhstan. Its core operations encompass production of electricity and heat, transmission, distribution and sale of electricity, thermal coal mining. The Company is dedicated to implementing a cohesive state policy within the power industry. This commitment involves the modernization, reconstruction, and construction of power generation facilities. These efforts are aimed at bolstering Kazakhstan's energy security and ensuring a reliable energy supply for the nation's growth and development.

Blog Of The Chairman Of The Board

Dear visitors of the blog! I thank You for your interest in my personal blog. In turn, I will try to answer all your questions regarding the work of our Company or its subsidiaries and affiliates. I hope that our communication will help you form an objective opinion about Samruk-Energo JSC.

Go to the blog
blog pred

«Samruk-Energy» JSC investment projects

Group of companies

Central office

Generation companies

Distribution companies

HPP

RES

Coal companies

31.8%

from total electricity generation in Kazakhstan

25.5%

from the total installed capacity of stations in the unified energy system of the Republic of Kazakhstan

37.3%

from the volume of coal production in Kazakhstan

965.846

million tenge аssets

map

Useful links

The Project “Retrofit of Shardarinsk HPP”

The Project “Retrofit of Shardarinsk HPP”

photo5 SHARGES

The project description: The project relates to power industry and focuses on ensuring reliable operation of the existing hydropower plant and increasing capacity to cover the energy needs in the region. The project was implemented to upgrade the existing production by retrofitting the existing HPP equipment using up-to-date technologies, which resulted in an increase in the capacity of the hydropower plant from 100 MW to 126 MW, greater reliability of its operation and reduction of the risk of accidents.

The project goals:

  • Replacement of obsolete equipment to increase the performance and safety of the plant’s operation;
  • an increase in the station's installed capacity by 26% (from 100 MW to 126 MW) and electricity generation to cover the growing electricity supply shortage in the region;
  • increasing the efficiency of the station by reducing the direct costs associated with the repair and maintenance of equipment;
  • Increasing the station's capacity by upgrading the existing equipment;
  • improve reliability of equipment operation and mitigate the risk of accidents.

The project implementation period: 2010-2020

Status:

The Certificate on acceptance of the power facility into operation was signed on August 28, 2020.