SAMRUK ENERGY

EFFICIENT HIGH-TECH
OPERATING ENERGY COMPANY

News

23.04.24

Samruk-Energy subsidiaries continue to assist those affected by the flooding.

23.04.24

CHP-1: Repair work progressing as planned

22.04.24

"Samruk-Energy" JSC employees played an active role in the republican environmental campaign “Clean Kazakhstan”

About company

"Samruk-Energy" JSC is the largest diversified electric power holding company with a primary objective of establishing a highly efficient energy supply system to support the sustainable development of all sectors in Kazakhstan. Its core operations encompass production of electricity and heat, transmission, distribution and sale of electricity, thermal coal mining. The Company is dedicated to implementing a cohesive state policy within the power industry. This commitment involves the modernization, reconstruction, and construction of power generation facilities. These efforts are aimed at bolstering Kazakhstan's energy security and ensuring a reliable energy supply for the nation's growth and development.

Blog Of The Chairman Of The Board

Dear visitors of the blog! I thank You for your interest in my personal blog. In turn, I will try to answer all your questions regarding the work of our Company or its subsidiaries and affiliates. I hope that our communication will help you form an objective opinion about Samruk-Energo JSC.

Go to the blog
blog pred

«Samruk-Energy» JSC investment projects

Group of companies

Central office

Generation companies

Distribution companies

HPP

RES

Coal companies

31.8%

from total electricity generation in Kazakhstan

25.5%

from the total installed capacity of stations in the unified energy system of the Republic of Kazakhstan

37.3%

from the volume of coal production in Kazakhstan

965.846

million tenge аssets

map

Useful links

The Project “TRANSITION TO CONTINUOUS AND CYCLICAL TECHNOLOGY OF EXTRACTION, TRANSPORTATION, BLENDING AND LOADING OF COAL IN THE BOGATYR OPEN-PIT MINE”

The Project “TRANSITION TO CONTINUOUS AND CYCLICAL TECHNOLOGY OF EXTRACTION, TRANSPORTATION, BLENDING AND LOADING OF COAL IN THE BOGATYR OPEN-PIT MINE”

photo13 Bogatyr komir

Project Purpose:

The project involves a phased transition of the Bogatyr open pit mine to a flow technology of coal delivery by conveyor transport to near-surface averaging warehouses, followed by its loading at surface loading facilities. Increase the production capacity of the enterprise. Replace worn-out fixed assets at coal shipment, crushing and transporting.

Implementation period: 2013-2023.

Expected impact:

- Increase in production capacity of Bogatyr open pit mine from 32 million tons to 40 million tons of coal per year;

- Increase in labour productivity by 25%;

- Reduction of wagon turnover time by 2.5 times (from 14.3 to 5.4 hours) and introduction of processes for precise loading of coal without uncoupling of railway trains.

Current project status:

ThyssenKrupp equipment has been 100% delivered; construction and installation works have been completed. Start-up and adjustment works of electrical equipment of the following facilities are in progress: Stacker, Crushing and Trans loading points, hoisting belt conveyor, drum reclaimer. In December 2022, a test run with coal shipment to Astana CHPP was made.

Planned activities under the Project:

- Completion of commissioning works - III quarter of 2023.

- Commissioning - IV quarter 2023.