SAMRUK ENERGY

EFFICIENT HIGH-TECH
OPERATING ENERGY COMPANY

News

10.05.24

Samruk-Green Energy successfully sells over 12,000 green certificates

09.05.24

Victory Day congratulations from Kairat Maxutov, Chairman of the Board of “Samruk-Energy” JSC

06.05.24

Announcing the winners of the children's drawing contest

About company

"Samruk-Energy" JSC is the largest diversified electric power holding company with a primary objective of establishing a highly efficient energy supply system to support the sustainable development of all sectors in Kazakhstan. Its core operations encompass production of electricity and heat, transmission, distribution and sale of electricity, thermal coal mining. The Company is dedicated to implementing a cohesive state policy within the power industry. This commitment involves the modernization, reconstruction, and construction of power generation facilities. These efforts are aimed at bolstering Kazakhstan's energy security and ensuring a reliable energy supply for the nation's growth and development.

Blog Of The Chairman Of The Board

Dear visitors of the blog! I thank You for your interest in my personal blog. In turn, I will try to answer all your questions regarding the work of our Company or its subsidiaries and affiliates. I hope that our communication will help you form an objective opinion about Samruk-Energo JSC.

Go to the blog
blog pred

«Samruk-Energy» JSC investment projects

Group of companies

Central office

Generation companies

Distribution companies

HPP

RES

Coal companies

31.8%

from total electricity generation in Kazakhstan

25.5%

from the total installed capacity of stations in the unified energy system of the Republic of Kazakhstan

37.3%

from the volume of coal production in Kazakhstan

965.846

million tenge аssets

map

Useful links

 Project “CONSTRUCTION OF 50 MW WPP IN THE VICINITY OF EREYMENTAU CITY”

Project “CONSTRUCTION OF 50 MW WPP IN THE VICINITY OF EREYMENTAU CITY”

photo9 EWP

The project title: “Construction of 50 MW wind power plant in the vicinity of Ereymentau city”.

The project implementation goal: The project addresses one of production tasks of “Samruk-Energy” JSC - minimization of adverse environmental impact through the reduction of greenhouse gas emissions. The issue of implementing such projects is among the priorities for meeting international commitments of the Republic of Kazakhstan to reduce greenhouse gas emissions in accordance with the UN Framework Convention on Climate Change, to which the Republic of Kazakhstan has been a party since 1997. The implementation of the Project is in line with the mission and main strategic goals of “Samruk-Energy” JSC:

- Reliable and high-quality supply of electricity produced using renewable energy sources;

- Design and construction of facilities for the use of renewable energy sources;

- Production and sale of electrical energy using renewable energy sources.

The project description: The selected site near Ereymentau city fits for the construction of a wind power plant because of good wind potential with an average speed of 8.5 m/s. Possibility of connecting to power grids for output of WPP power has been agreed.

 

Implementation period: 2011-2022

 

Status: Currently, the works on the construction of access and on-site roads, setting of installation sites for wind turbines (wind turbine foundations), on the reconstruction of existing power lines and laying of 35 kV cable lines, on the construction of SS-220 / 35 kV (CR, CCR, SCP buildings have been built) are underway.

 

Planned events:

- Supply and installation of wind turbines, completion of construction and installation works for SS-220/35kV and overhead lines 220kV.

- Commissioning – 4th quarter of 2022.