Construction of 2 MW solar power plant in Kapshagay city

Construction of 2 MW solar power plant in Kapshagay city

Project title

  • Construction of 2 MW solar power plant in Kapshagay city

Purpose

  • The use of renewable energy sources.
  • Reducing the level of hydrocarbons use in electricity production

Implementation period

  • 2011 – 2013

Project cost

  • 1 700,1 mln.KZT

Performance characteristics

  • Rated capacity – 2 MW
  • Monocrystalline panels manufactured by  «BISOL Central Asia Ltd»
  • Panel’s efficiency – 15,3%
  • 70% fixed and 30% tracking structures (trackers)
  • 61 trackers (2379 panels -  39 panels on each tracker)
  • 351 fixed structure (total 5616 panels -  16 panels on each fixed structure)
  • Totally 7995 solar panels
  • 178 inverters
  • ICUF – 20%

Effect

  • Power plant’s performance – 3,6 mln.kWh/year.

Number of jobs

  • During operation –  5 persons

Current status

  • The power plant was put into operation in 2013