Project description

  • Construction of wind power plant with rated capacity of 45 MW and potential expansion up to 300 MW near Ereymentau city

Purpose

  • Increasing RES share in electricity production
  • Reducing the level of hydrocarbons use in electricity production. 

Implementation period

  • 2011 – 2015

Project cost

  • 19 214 mln.KZT

Performance characteristics

  • Installed capacity - 45 MW

Effect

  • Production of about 172,2 mln.kWh electricity per year
  • Estimated ICUF – 41%

Number of jobs

  • During construction – 150 persons
  • During operation –  8 persons

Current status

  • The power plant was put into operation in 2015.