“Almaty Power Plants” JSC: Commissioning of boiler unit No.8 of Almaty CHP-2

The ceremony of the boiler unit No.8 commissioning as part of reconstruction and expansion of Almaty CHP-2 was held on September 21, 2016

The ceremony of the boiler unit No.8 commissioning as part of reconstruction and expansion of Almaty CHP-2 was held on September 21, 2016.  The launch ceremony was attended by B. Baibek, Mayor of Almaty city, Almassadam Satkaliyev, Chairman of the Board of "Samruk-Energy" JSC, Mukhamed-Rakhimov N., Chairman of the Board of "Almaty Power Plants" JSC.

The commissioning of new boiler will ensure the growing needs of the city - new facilities of "Universiade-2017", industrial zone and housing development under "Affordable Housing - 2020" program - said Satkaliyev Almassadam, "Samruk-Energy" JSC Chairman of the Board.

The project cost is 25,7 billion tenge. Commissioning of the boiler unit No.8 increase thermal capacity of CHP-2 by 20% from 1176 to 1414 Gcal / h and will provide production of additional 450 million KWh of electricity per year.


For reference:

Boiler dimensions:  

  • weight: 3265 tons
  • depth – 20 m, width – 14,5 m.
  • height: 42 meters;
  • The size of furnace chamber - 1900 c.m.
  • water volume - 83 c.m.
  • Steam volume - 71 c.m.

basic parameters:

  • nominal capacity - 420 tons/hour
  • steam temperature - 560°С             
  • steam pressure – 140 atm
  • Efficiency coefficient – not less than 92,3 %           
  • with improved environmental performance

Contacts:

  • www.ales.kz
  • tel.: +7 (727) 227 70 18, +7 (701)7275544
2016.09.21
2016.09.21