Project title
- Construction of 300 MW Moynak HPP on Charyn river
Purpose
- Commissioning of maneuverable source of electricity to cover the electricity demand of Kazakhstan’s southern zone.
Implementation period
Project cost
Performance characteristics
- Rated capacity - 300 MW
- Maximum water discharge – 74,0 m3/sec
- ICUF – 39,1%
- Parameters of Bestubinsk water reservoir
- FSL – 1770 m
- DSL– 1736 m
- Reservoir capacity:
- Total – 238 mln. m3
- Useful – 198 mln. m3
- Downstream elevation – 1242,5m
Effect
- Electricity production of 1,027 bln. kWh annually
Number of jobs
- During construction – 645 persons
- During operation – 127 persons
Current status
- The power plant was put into operation in 2012